How a mezzanine floor works

Columns every 4 to 8 mDeck: 250 to 2,000 kg/m²Pallet gateStairsSide view: free-standing steel, a whole new level
  1. Columns are set out across the floor, usually 4 to 8 metres apart.
  2. Main beams and secondary beams form the frame and carry the deck.
  3. The deck goes down: chipboard as standard, or chequer plate or coated board.
  4. Handrails, stairs and pallet safety gates finish the edges.
Uses
Storage, picking, offices, production
Loads
Foot traffic to heavy pallets
Structure
Free-standing steel
Later
Can be taken down and moved

Is it right for you?

A good fit, and when to look elsewhere

A good fit for

  • Buildings with height to spare
  • Adding space without moving or extending
  • Offices or packing areas above storage
  • Heavy loads on the upper level

Consider something else if

Components and options

What goes into it

01

Columns

Carry the whole structure. Sized for height, load and spacing.

02

Main and secondary beams

Form the frame and support the deck; can overhang where the building needs it.

03

Bracing

Keeps it rigid. Braceless designs leave room for trucks underneath.

04

Decking

Chipboard as standard; chequer plate or textured coated boards for grip and wear.

05

Handrails and stairs

All-steel handrails; stairs with rails both sides and landings if needed.

06

Pallet safety gate

Lets pallets up by forklift without ever leaving the edge open.

Buying guide

Specifying a mezzanine floor

  • Floor loading. Around 250 to 350 kg/m² covers offices and light storage; heavier storage, shelving and pallets need higher ratings, up to about 2,000 kg/m². The rating is fixed at design, so plan for what the floor will carry in the future, not just today.
  • Height. The building needs enough clear height for comfortable headroom both under and on top of the floor.
  • Columns and span. Wider column spacing leaves more usable space underneath but needs heavier steel. Around 4 to 8 m is usually the most economical.
  • The existing floor. Each column puts a point load on the slab, so the slab has to be checked, and sometimes pads are needed under the columns.
  • Access. Stairs, pallet gates and, where needed, a goods lift.

Buying guide

What affects the price

  • Floor area and the load rating.
  • Column spacing and height.
  • Fire protection, where Building Regulations require it.
  • Decking, handrails, stairs, pallet gates and lifts.
  • Services such as lighting, sprinklers and power, and any partitioning for offices.

Buying guide

Building Regulations and fire safety

A mezzanine floor normally needs Building Regulations approval, because it changes how the building is used and how people escape from it. Building Control will look at the structure, escape routes and travel distances, the stairs and handrails, and fire protection, which depends on the floor's size, what it is used for and how it relates to the rest of the building. Planning permission is not usually needed for a mezzanine inside an existing building, but check with your local authority, particularly for retail use.

Once in use, keep the floor within its rated load, shown on a load notice, and include it in the site's regular checks.

Racking and trucks, sized together

The trucks that work it

Racking and trucks decide each other: aisle width, top beam height and capacity at height all have to match. We supply both, so we check them together.

Tell us what you store, and we will tell you what fits

Every building is different, so we start with a free site survey: pallet or product sizes and weights, how many locations, how fast stock moves, the clear height and the trucks you run. We come back with a design and a price, install it, and inspect it once it is in use.

Mezzanine floors: common questions

Floors are designed for their use, with ratings from 250 kg/m² for foot traffic and light storage up to 2,000 kg/m² for heavy shelving and pallets.

Yes. It is a free-standing steel structure, not part of the building, so it can be taken down and rebuilt elsewhere.

By forklift through a pallet safety gate, which never leaves the edge open, or by a goods lift.

Normally, yes. Building Control looks at the structure, escape routes, stairs and handrails, and fire protection, which depends on the floor's size and use.

Not usually, for a mezzanine inside an existing building. It can be needed in some cases, particularly for retail use, so check with your local authority.

It depends on your building and what the floor will carry: the area, load rating, height, column spacing, fire protection, and extras such as stairs, pallet gates, lifts, lighting and partitioning. We price from a free site survey.

It needs enough clear height, puts point loads on the existing slab, usually needs Building Regulations approval, and the load rating is fixed at design, so a floor planned for light storage cannot later take pallets. Columns also take some space on the floor below.